Stek victorious for Liander in preliminary relief procedure on permitted usage electricity connection

Stek has successfully represented energy distribution company Liander in a preliminary relief procedure before the District Court Gelderland. The procedure had been initiated by a large customer (a printing house), claiming that it was entitled to a large amount of contracted capacity. The court sided with Liander that this claim is without merit and awarded the counterclaim of Liander, ending the excess usage of the customer on the existing connection.

Please click here for the judgment of the Gelderland District Court of 9 November 2020 (in Dutch).